1. Milestone-Based Financial Offer
Arybit Technologies submits this financial offer as a fixed lump-sum schedule aligned to the six contractual milestones of Tender Reference UNDP-GHA-00537-2. The total contract price is GHS 6,300,000.00.
The commercial response entered in the Oracle Supplier Portal uses the milestone allocation and promised delivery dates shown below.
| Ref. | Deliverable | Amount (GHS) | % of Total | Promised Delivery Date |
|---|---|---|---|---|
| M1 | Approved Inception Report | 630,000.00 | 10% | 28 September 2026 |
| M2 | Approved Requirements Specification and Technical Design Note | 945,000.00 | 15% | 26 October 2026 |
| M3 | Approved Wireframes and UI/UX Designs | 630,000.00 | 10% | 23 November 2026 |
| M4 | Functional Prototype System Developed | 1,575,000.00 | 25% | 18 January 2027 |
| M5 | Backend, Database, Testing and UAT Completed | 1,575,000.00 | 25% | 15 February 2027 |
| M6 | Deployment, Training, Documentation and Final Handover Completed | 945,000.00 | 15% | 15 March 2027 |
| Total Contract Price | GHS 6,300,000.00 | 100% | 28 Weeks | |
The promised delivery dates correspond to the proposed milestone schedule of Week 4, Week 8, Week 12, Week 20, Week 24 and Week 28 respectively.
Milestone Timeline Reconciliation
| Milestone | Target Week | Promised Delivery Date | Commercial Trigger |
|---|---|---|---|
| M1 | Week 4 | 28 September 2026 | Inception approval |
| M2 | Week 8 | 26 October 2026 | Requirements specification and technical design approval |
| M3 | Week 12 | 23 November 2026 | UI/UX approval |
| M4 | Week 20 | 18 January 2027 | Prototype acceptance |
| M5 | Week 24 | 15 February 2027 | UAT acceptance |
| M6 | Week 28 | 15 March 2027 | Final deployment and handover acceptance |